Here's an explanation of the calculations that you can find in the labour costs section of a scheduled shift or time entry.
There are two different calculations. You can either use a conversion factor or enter the cost per hour individually per team member.
Labour costs using a conversion factor
Hours = The time between the start and end of the shift, minus any breaks.
Hourly wage = The team member’s gross hourly wage as stated in their contract.
Conversion factor = The multiplier set in the contract settings to account for employer costs, such as employer taxes and contributions.*
Labour cost = The estimated cost of the shift. Eitje multiplies the hours by the team member’s gross hourly wage and then by the conversion factor.
*A team member’s contract states their gross hourly wage. To include additional employer costs in your labour cost calculation, set a conversion factor for each contract type.
Open the menu in the top right corner and go to Company settings > Financial > Contracts. Your accountant can help you choose the right conversion factor.
Labour costs using the cost per hour
Hours = The time between the start and end of the shift, minus any breaks.
Cost per hour = If you know a team member’s exact labour cost per hour, open their profile and click All details. Enter the amount in the Labour costs per hour field at the bottom of the screen.
Labour cost = The estimated cost of the shift. Eitje multiplies the hours by the team member’s cost per hour.
You can enter labour costs per hour for each team member, while the conversion factor is set per contract type. If you fill in the Labour costs per hour field, Eitje uses that exact amount and ignores the conversion factor for that team member. Keeping these amounts up to date helps you estimate labour costs more accurately.
If you use an integration with Nmbrs and have enabled labour costs per hour there, Eitje imports them automatically. Otherwise, you’ll need to update the Labour costs per hour field manually, including when the salary in the team member’s contract changes.
Labour costs including allowances
You can enable allowances in Eitje to pay team members extra, for example when they work night shifts or on public holidays. Eitje includes these allowances in labour costs. In the scheduled shift or time entry you can see whether an allowance applies.
Here’s an example of how an allowance appears in the labour cost breakdown:
Allowance factor = Allowance overlap × Allowance weight
Allowance overlap (only for unsocial hours allowances) — The share of the shift covered by the allowance. Use 1 if it covers the whole shift or 0.5 if it covers half.
Allowance weight = The multiplier based on the allowance percentage. A 50% allowance has a weight of 1.5.
Which hours are included?
Included | Not included |
Worked hours: Approved | Scheduled time entries |
Worked hours: Pending | Hour type: Leave |
Hour type: Sick leave |
|
Hour type: Special leave |
|
Eitje uses the shifts in your schedule to forecast labour costs. Time entries for leave, sick leave and special leave are excluded from the forecast. The table above shows which hours count towards actual labour costs.
Scheduled time entries are created from the schedule and show when a team member was expected to work. Eitje needs the recorded worked hours to know whether the team member worked the shift at all.
Leave hours are excluded from actual labour costs so you can see how much it costs to staff your shifts. To account for the cost of leave, include it in the conversion factor or in the labour costs per hour you enter for each team member.